Case study
From commercial scrutiny to a better hospital handover
Capital project assurance at Birmingham Women’s and Children’s
“The support you've both provided has been first class, and you've made a genuine difference to how we manage our capital programme.”
Birmingham Women’s and Children’s NHS Foundation Trust
A hospital construction project leaves more than a completed building behind. The estates team needs the records, certificates and operating information to maintain it—and a clear understanding of the decisions made along the way.
Subiaco supported Birmingham Women’s and Children’s with cost assurance across its capital programme. Working with the infrastructure team, Amir Shafie and Graham Woodhouse helped examine commercial issues and develop a more consistent approach to project governance, information and handover.
Making the decisions clearer
The assignment began with reviewing costs, programme information and risk across several construction workstreams. It highlighted an opportunity to strengthen the process connecting those elements: what information was needed, who should review it and when a project was ready to move forward.
Subiaco developed a Gateway framework aligned with the RIBA Plan of Work. It established defined stages from initial brief through delivery and close-out, with supporting information and approvals required at each step.
The team also produced practical templates for meetings, approval records, completion and handover, alongside guidance on operation and maintenance documentation. Regular support helped the estates team apply the framework to individual projects.
Turning the framework into a practical result
The MRI project provided a clear example of the approach in use.
Subiaco supported the handover and close-out process, helping the team assemble the documentation needed to operate and maintain the completed facilities. Its February 2026 implementation review recorded that essential project information, operation and maintenance manuals and statutory certificates had been brought together and were already being used to plan maintenance.
That gave the process a practical purpose beyond completing paperwork: helping the estates team prepare for its responsibilities after construction.
A contribution beyond the cost report
The work combined commercial scrutiny with a repeatable structure for decisions and project handover.
The MRI workstream demonstrated the benefits of applying that structure. Subiaco’s review also identified further steps needed to embed it consistently across the wider programme, giving the client a clear basis for continuing improvement.